Power Boiler DA Tank Replacement

Madison Industrial Services Team, Ltd. provided planning, engineering, and construction services to safely replace a 20 ton Deaerator tank at an Arkansas paper mill utilizing a cantilever rigging beam with traveling counterweight. The center of gravity of the vessel was located at 60′ elevation, 30′ in from the edge of the structure, at a 70′ lift radius. This innovative rigging approach was chosen over more traditional approaches utilizing elevated tracks, skids and rollers to enhance safety and reduce the cost and schedule duration of the work.